Important  Terms and Factors:
The variable load problem has introduced the following terms and factors in power plant engineering:
(i) Connected load. It is the sum of continuous ratings of all the equipment connected to supply system.
A power station supplies load to thousands of consumers.Each consumer has certain equipment installed in his premises.The sum of the continuous ratings of all the equipment in the  consumer’s premises is the “connected load” of the consumer.For instance, if a consumer has connections of five 100-watt lamps and a power point of 500 watts, then connected load of the consumer is 5 × 100+500=1000 watts.The sum of the connected loads of all the consumers is the connected load to the power station.
(ii) Maximum demand: It is the greatest demand of load on the power station during a  given period.
The load on the power station varies from time to time.The maximum of all the demands that have occurred during a given period (say a day) is the maximum demand.Thus referring  to the load curve shown in Figure, the maximum demand on the power station during the day is 6 MW and it occurs at 6 P.M. Maximum demand is generally less than the connected load because all the consumers do not switch on their connected load to the system at a time. The knowledge of maximum demand is very important as it helps in determining the installed capacity of the station.The station must be capable of meeting the maximum demand.
Daily Load Curve
(iii) Demand factor: It is the ratio of maximum demand on the power station to its connected load i.e.,
                                Demand factor =Maximum demand/Connected load
The value of demand factor is usually less than 1. It is expected because maximum demand on the power station is generally less than the connected load.If the maximum demand on the power station is 80 MW and the connected load is 100 MW, then demand factor = 80/100 = 0·8.  The knowledge of demand factor is vital in determining the capacity of the plant equipment.
(iv) Average load. The average of loads occurring on the power station in a given period(day or month or year)  is known as  average load  or  average demand.
            Daily average load =No.  of units (kWh) generated in a day/24 hours
      Monthly average load =No. of units (kWh) generated in a month/Number of hours in a month
          Yearly average load = No. of units (kWh) generated in a year/8760 hours
(v) Load factor. The ratio of average load to the maximum demand during a given period is known as load factor  i.e .,
                                      Load factor = Average load/Max. demand
If the plant is in operation for T hours,
                                 Load factor = Average load× T/Max. demand× T
                                                       =Units generated in T hours/Max. demand ×T hours 
The load factor may be daily load factor, monthly load factor or annual load factor if the time
period considered is a day or month or year.Load factor is always less than 1 because average load is smaller than the maximum demand.The load factor plays key role in determining the overall cost per unit generated.  Higher the load factor of the power station, lesser  will be the cost per unit generated.
(vi) Diversity factor. The ratio of the sum of individual maximum demands to the maximum demand on power station is known as  diversity factor i.e.,
   Diversity factor = Sum of individual max.  demands/Max. demand on power station
A power station supplies load to various types of consumers whose maximum demands generally do not occur at the same time.Therefore, the maximum demand on the power station is always less than the sum of individual maximum demands of the consumers. Obviously, diversity factor will always be greater than 1. The greater the diversity factor, the lesser  is the cost of generation of power.
(vii) Plant capacity factor. It is the ratio of actual energy  produced to the maximum possible energy that could have been produced during a given period i.e.,

   Plant capacity factor =Actual energy produced/Max. energy that could have been produced
                                         =Average demand ×T/Plant capacity ×T
                                         =Average demand/Plant capacity
Thus if the considered period is one year,
              Annual plant capacity factor = Annual kWh output/Plant capacity × 8760 
The plant capacity factor is an indication of the reserve capacity of the plant. A power station is so designed that it has some reserve capacity for meeting the increased load demand in future. Therefore, the installed capacity of the plant is always somewhat greater than the maximum demand on the plant.
                          Reserve capacity = Plant capacity −  Max. demand
It is interesting to note that difference between load factor and plant capacity factor is an indication of reserve capacity.If the maximum demand on the plant is equal to the plant capacity, then load factor and plant capacity factor will have the same value.In such a case, the plant will have no reserve capacity.
(viii) Plant Use Factor. It is ratio of kWh generated to the product of plant capacity and the number of hours for which the plant was in operation i.e.
             Plant use factor = Station output in kWh/Plant capacity × Hours of use 

Units  Generated  per  Annum:
It is often required to find the kWh generated per annum from maximum demand and load factor.
The procedure is as follows :
                             Load factor = Average load /Max. demand
                      ∴ Average load = Max. demand  ×  L.F.
       Units generated/annum= Average load (in kW)  ×  Hours in a year
                                                   = Max. demand (in kW) ×  L.F. ×  8760